Answer question numbers 3 ( a ) to 3 (d) on the basis of your understanding of the following paragraph and the related studies concepts. The Tehri dam is the highest dam in India and one of the highest in the World. The Tehri dam withholds a reservoir of capacity 4.0 km 3 and surface area 52 km 2 . It is used for irrigation, municipal water supply and the generation of 1000 MW of hydroelectricity.
The Tehri dam has been the object of protests. Environment activist Shri Sunder Lal Bahuguna led the "Anti Tehri Dam Movement" from 1980s to 2014 . The protest was against the displacement of town inhabitants and environmental consequences of the weak ecosystem. The relocation of more than1 , 00 , 000 people from the area has led to protracted legal battles over resettlement rights and ultimately resulted in the delayed completion of the project.
(a) How is hydropower harnessed?
(b) Define1 MW .
(c) Mention two disadvantages of constructing Tehri Dam.
(d) What happens when water from great heights is made to fall on blades of turbine?
The Tehri dam has been the object of protests. Environment activist Shri Sunder Lal Bahuguna led the "Anti Tehri Dam Movement" from 1980s to 2014 . The protest was against the displacement of town inhabitants and environmental consequences of the weak ecosystem. The relocation of more than
(a) How is hydropower harnessed?
(b) Define
(c) Mention two disadvantages of constructing Tehri Dam.
(d) What happens when water from great heights is made to fall on blades of turbine?
Solution:
© examsnet.com
Go to Question: