Given: A and B together can finish a work in 45 days
They worked for it for 36 days and then B left the work
The remaining work was done by A alone in 16 days more
Concept Used: Work done in 1 day by a worker
= Where n = Number of days to complete a work by the worker
Calculation: Work done by A and B together in one day
= Work done by A and B together in 36 days
== Amount of work left when B left the work
=1–= Work done by A alone in one day
== Time taken by A alone to finish the work
==80 days