Given: A, B and C can do a piece of work in 24, 20 and 40 days respectively C left the work 4 days before the completion of the work Calculation: Speed of A = work to do / time it takes to do the work =241​ Speed of B = work to do / time it takes to do work =201​ Speed of C =401​. When they work together they take t days to complete the work with the given condition. So according to equation: ⇒ Work done by A=24t​ ⇒ Work done by B=20t​ ⇒ Work done by C=40t−4​ So, According to the question 24t​+20t​+40t−4​=1∴ Time taken t = 9.43 days.