(a)
Quantity A : Let total units of work = 120 units (LCM of 12, 15and 24)
⇒ Efficiency of P and Q together =
12120​=10 ⇒Efficiency of Q and R together =
15120​=8 ⇒ Efficiency of R and P together =
24120​=5 ⇒ Efficiency of P, Q and R together =
210+8+5​ =
223​ days
⇒ Efficiency of Q =
223​−5=213​ ⇒ Time taken by Q to finish the work alone
=13120×2​ days
=
13240​ days
Quantity B : Let total units of work = 30 units (LCM of 10 and 15)
⇒ Efficiency of S =
1030​=3 ⇒ Efficiency of T =
1560​=2 Since S left after 5 days.
Unit of work left after 5 days =
30−5×(3+2)=5 units
⇒ Time taken by T to finish the remaining work
=
25​=2.5 days
⇒ Total time to finish the whole work = 5 + 2.5 days
= 7.5 days
∴ Quantity A > Quantity B