Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
CBSE
CBSE Question Papers
NCERT Books
NCERT Exemplar Books
NCERT Study Notes
CBSE Study Concepts
CBSE Class 10 Solutions
CBSE Class 12 Solutions
NCERT Text Book Class 11 Solutions
NCERT Text Book Class 12 Solutions
ICSE Class 10 Papers
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Contact Us
Our Apps
Privacy
Test Index
Time and Work Practice Test 1 with solutions
Show Para
Hide Para
Share question:
© examsnet.com
Question : 38
Total: 40
A civil engineer fixed a schedule to finish a certain project in 360 days with the help of 90 workers. After 90 days of work, he employed 90 more workers in order to finish the work before time. Find the number of days saved.
360 days
225 days
270 days
135 days
180 days
Validate
Solution:
👈: Video Solution
Work done by 90 workers in 1 day =
1
360
Work done by 90 workers in 90 days
=
90
×
1
360
=
1
4
Remaining work 1 -
1
4
=
3
4
90 more workers have joined, so total workers = 180
If 90 workers finish work in 360 days, then 180 workers finish the work in 180 days
So,
3
4
th part of work is done by 180 workers in
180
×
3
4
= 135 days.
Time taken to complete the work = 90 + 135 = 225
Number of days saved = 360 - 225 = 135 days.
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
Prev Question
Next Question