Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Careers
Contact Us
Our Apps
Privacy
Test Index
Time and Work Practice Test 1 with solutions
Show Para
Hide Para
Share question:
© examsnet.com
Question : 7
Total: 40
Six persons working 6 hours a day can complete a work in 12 days. When they have worked for 6 days, 2 persons left the job and the remaining workers started working for 8 hours a day. In how many days can the remaining work be completed?
6 days
61
4
days
5
1
2
days
6
3
4
days
5
4
5
days
Validate
Solution:
👈: Video Solution
If 6 persons working 6 hours a day can finish the work in 12 days, then in 6 days half of the work will be done.
So, remaining work =
1
2
If 6 workers working 6 hours a day can finish the work in 12 days,
then 4 workers working 8 hours a day can finish the work in
6
×
6
×
12
=
4
×
8
×
days
days =
6
×
6
×
12
4
×
8
=
27
2
days.
Then time taken to complete
1
2
of the work
=
27
2
×
2
=
27
4
=
6
3
4
days
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
Prev Question
Next Question