Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Careers
Contact Us
Our Apps
Privacy
Test Index
Time and Work Practice Test 4 with solutions
Show Para
Hide Para
Share question:
© examsnet.com
Question : 37
Total: 40
12 men take 36 days to do a work while 12 women complete 3/4 th of the same work in 36 days. In how many days 10 men and 8 women together will complete the same work?
27 days
12 days
6 days
Data inadequate
Validate
Solution:
Ratio of work of a man and a woman = 1 :
3
4
= 4 : 3
Ratio of their time taking = 3 : 4
Hence, 4 women = 3 men
∴ 8 women = 6 men
Now, 10 men + 8 women = 10 men + 6 men = 16 men
Again, 12 men can complete the work in 36 days
Hence, 16 men will complete the work in
12
×
36
16
= 27 days.
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
Prev Question
Next Question