Vinber Ltd., set up a manufacturing unit at Bhiwadi in Himachal Pradesh to manufacture electric geysers and supply them to dealers all over the country. Their production target was 500 geysers per week. It was decided by the management that variation in production upto 10 units would be acceptable.
At the end of the first week, the production was 450 geysers. The next week, production increased to 470 geysers. A week later, production was 460 geysers. On investigation, it was found that fluctuation in production was due to irregular supply of electricity.
At the end of the first week, the production was 450 geysers. The next week, production increased to 470 geysers. A week later, production was 460 geysers. On investigation, it was found that fluctuation in production was due to irregular supply of electricity.
© examsnet.com
Question : 23
Total: 40
Also, state the step(s) that have not been discussed in the above para.
Solution:
Steps not discussed in the above para is: Taking corrective action if deviations go beyond the acceptable limits.