Formula Used:W1M1D1=W2M2D2 Where, M = Number of men, D = number of days, W = Amount of work Calculation: We have total Scheduled time = 180 days 5th1 of the scheduled time =5180=36 days According to the given information, 120 labors can do 6th1 of the total work in 36 days ⇒ remaining work =6th5 of total work According to the formula used ⇒ 61120×36=65M2×144 ⇒ M2=150∴ Additional Labours required = 150 – 120 = 30