The project scope has likely not been properly identified, so the project is taking longer than it should. 1 is incorrect. There is no evidence in the information presented that the project should be broken into subprojects. 3 is incorrect. The project team may not have the power to approve or disapprove changes. In addition, the question’s information does not provide adequate information to determine whether changes are the root of the problem. 4 is incorrect. There is not enough information presented to determine that the project should be stopped.