The contractual agreement between the vendor and the customer override all other documents. 1 is incorrect. The change control system should comply with the contractual agreement between the vendor and the customer. 2 is incorrect because the scope details the project work, not the contractual obligations between the vendor and the customer. 3 is also incorrect because the procurement management plan is not as specific as the terms defined within the contract.