When a risk depletes the contingency reserve it calls for reserve analysis in relation to the amount of remaining risks within the project. 1 is incorrect because the project likely won’t need to cancelled because of the risk event. 2 is incorrect because this event is iterative. 4 is incorrect because there’s no evidence yet if additional funds are needed.