The project sponsor does ensure that the project manager has the necessary resources to complete the project. 1 is incorrect because the project sponsor does not manage with the project manager. 2 is incorrect because the project sponsor does not assign project team members to activities, the project manager does. 3 is also incorrect because a project manager has little to no authority in a functional environment.