The CPI is found through the formula EV/A3. In this instance the EV is $250,000 – 100 percent of the BAC because the project is complete. 2 is incorrect because this is the final AC for the project. 3 is incorrect because this is the cost variance for the project. 4 is incorrect because the EV information is supplied in the question.