The project charter has already been created because it authorizes the project. 2 is incorrect. Risk does not need to be examined again because the change may introduce risk concerns into the project. 3 is incorrect. The schedule will need to be examined because the changes may cause the current schedule to change. 4 is also incorrect. The changes may bring additional costs with them so the project costs will need to be examined.