An assumption is something that you cannot prove to be true, such as the summer weather, but you believe it to be true. 1 is incorrect as management reserve describes a portion of time allotted for schedule overruns within the project work. 3 is incorrect as a constraint limits the project team’s options. 4 is incorrect as a project risk is an uncertain event that may have negative or positive impact on the project’s outcome.