The contract stipulates the terms for project acceptance. 1 is incorrect because a change request isn’t needed unless you are adding deliverables to the project scope. 2 is incorrect because the project sponsor may need to be included in the discussion, but the best choice is to consult the contract first. 4 is incorrect because the contract should be consulted before options of arbitration.