The earned value for this project is 20 percent complete. The formula is EV = % complete × BA3. 1 is incorrect. The EV is not a negative number since it is 20 percent complete. 3 is incorrect because $100,000 is the planned value amount. 4 is also incorrect because there is enough information to calculate the formula.