Because the goal of the kick-off meeting is to gain everyone’s commitment to the project. 1 is incorrect because the project goal is established before the kick-off meeting. 2 is incorrect because the project manager has likely already met the project team; in addition, this is not the goal of the meeting. 4 is incorrect because this statement is not valid.