Change is easily accepted in the beginning of a project; as the project moves toward completion change is harder to incorporate. 2 is incorrect. Risk is only accepted based on its impact of the project and the performing organization’s utility function. Recall that the utility function is an organization’s willingness to accept risk. 3 is incorrect. Team development happens throughout the project. 4 is incorrect. Scope verification happens throughout the project at phase completion, at major project deliverables, and at project completion.