The change control system that all changes should be formally documented. Undocumented change requests should not be processed or implemented. 1 is incorrect because the change may have been needed but the failure to follow the change control system prevents the change from entering the project scope. 2 is incorrect because there’s no mention of how much the change would cost the project. 3 is incorrect because there’s no mention of how much additional time the change would require.