Because the project team is assigned to many different projects and is not readily available for the project work, the project manager should develop a resource-limited schedule. 1 is incorrect. A team development plan is a subsidiary plan to train the project team on new or missing skills. 3 is incorrect because procurement is not an option in this instance. 4 is also incorrect because the responsibility assignment matrix is not needed at this time in the project.