Correct Answer is D. Analogous Estimating uses parameters such as duration, budget, size, weight and complexity from a previous similar project as the basis for estimating the same parameter or measure for a future project. Since the question specifically states that based on the experience gained from similar past projects, hence the estimation technique is Analogous.