This workaround allows the project team member to receive the software before the work package is schedule to start. 1 is incorrect because this will delay the project. 2 is incorrect because this workaround will increase costs and would be a waste of time. 4 is incorrect because there is no error with the shipping. A discount would not get the software to the project team member’s as needed.