Risk identification happens throughout the project life cycle. 1 is incorrect because risk identification happens throughout the project. 2 is incorrect. Risk identification is iterative and happens throughout the project. 4 is incorrect; the project customer may not know enough about the project’s discipline to understand when all of the risks have been identified. Risk identification is iterative and happens throughout the project.