The final project report should be created once the project is done. 1 is incorrect because the lessons learned documentation is created throughout the project, not just at the end. 3 is incorrect because there won’t always be bonuses, unfortunately. 4 is incorrect because all of the project deliverables are created throughout the project, not at the project’s end.