The schedule performance index (SPI) is calculated by dividing the earned value by the planned value. In this instance, the formula is $100,000 / 150,000 = .67. 1 is incorrect because this is the value of the cost performance index. 3 and 4 are incorrect because the SPI is not a dollar amount.