Because resource leveling will typically require the project duration to increase. 1 is incorrect because there is no evidence that more labor is available, approved, or allowed. 2 is incorrect because there’s no evidence that more funds will be needed to complete the project work. 3 is incorrect because the creation of the schedule will not necessarily take longer to create. The completion of the project will likely take longer, however.