In this instance, the pending law is a constraint on the project because it limits the project’s options. 1 is incorrect because the law is external to the project and wasn’t part of the project’s requirement for success. 2 is incorrect because the law is not part of the project scope, but an external factor that may affect the project scope. 3 is also incorrect because static isn’t a project management term that defines this scenario.