The previous project manager has made an assumption that there will be no delays when project team members travel. 1 is incorrect because this is not a constraint. 3 is incorrect because this is not a schedule variance, or if it is, there isn’t enough information provided to make this decision. 4 is also incorrect because there isn’t enough information provided to determine that this is a critical path activity.