The Schedule Performance Index (SPI) is calculated by dividing the Earned Value by the Planned Value. In this instance the formula is $100,000/150,000=.67. 1 is incorrect. This is the value of Cost Performance Index. 3 is incorrect. The SPI is not a dollar amount. 4 is incorrect. The SPI is not a dollar amount.