The WBS is the best tool for tracking project scope. 2 is incorrect because a network diagram illustrates the sequence of project activities. 3 is incorrect because QC involves methods to ensure the work meets the expected quality designed for the project. 4 is also incorrect. Risk event triggers are conditions that signal a risk event has occurred or is about to occur.