The project team creates the WBS. 1 is incorrect because the project manager doesn’t complete the WBS alone. 2 is incorrect because the project sponsor doesn’t complete the WBS. 4 is incorrect because the program manager doesn’t create the WBS for the individual projects within the program. The WBS creation is the responsibility of the project manager and the project team.