Interactions with other project managers aren’t included in the project archives – unless these interactions are specific to the project objectives. 1 is incorrect. Memos are part of the project records. 2 is incorrect. Vendor correspondence is part of the project records. 3 is incorrect. Faxes from project team members can be part of the project records.