Lessons Learned are not included in the project scope statement. Lessons learned are created throughout the project to reflect what has, and has not, worked well in the project. 1 is incorrect as project boundaries are included in the project scope statement. 2 is incorrect as the product acceptance criteria are included in the project scope statement. 3 is also incorrect project assumptions are included in the project scope statement.