The change in the cost of the connection should be documented in a cost variance report. 1 is incorrect. A formal presentation may or may not be necessary for the cost increase, but a cost variance report is needed. 2 is incorrect because a memo is not the appropriate report needed. 4 is incorrect because a memo from the contractor to management is also inappropriate.