A project with a CPI of .98 has to spend one dollar for every 98 cents of work it receives. 1 is incorrect because there’s no evidence that the project is late. 2 is incorrect because the project is actually losing money with this CPI, not making it. 4 is also incorrect since a CPI of .98 does not mean the project is 98 percent complete.