2 is correct because a self-organizing team is relatively autonomous regarding major decisions related to software development. 1, 3, and 4 are incorrect. 1 is incorrect because the distance between team members has no bearing on a team’s
choice to be self-organizing. 3 is incorrect because an agile team would not typically distribute assignments given by a typical manager. 4 is incorrect because there is no detailed examination typically within an agile project.