The correct answer is due to smaller work statements and less legal wrangling, the process is often faster. Because planning is done along the way, it’s likely that SOWs (Statement of Work) are shorter. SOWs scope information would be
less defined, or they’d be issued for smaller amounts of work. The other responses are incorrect because contracts are not discussed daily; they shouldn’t be evaluated daily or within a certain timebox; procurement is not always consistent
for all projects.