The correct answer is to expect changes while planning. Changes should not only be expected but welcomed; when they happen, they should influence the plan itself. The other responses are incorrect. When the first change is requested, nothing
of significance should occur; it all depends on the nature of the change. Additionally, a change does not imply that you should never estimate a release date; there’s no reason to ask for change suggestions at each meeting.