The correct answer is to deliver an MVP (minimum viable product) as quickly as possible. To prevent competitors from taking market share by getting their product out first, it’s most important to get an MVP out as soon as possible. The
other responses are incorrect because there’s no need for additional risk analysis; it’s not an agile practice to produce a fully featured product that can take longer and cost market share; in a competitive situation, further risk
logging is not an immediate focus.