Work packages are items at the lowest level of the WBS. A subproject is a smaller portion of the original project when a project is subdivided into more manageable components or pieces. A subproject WBS then breaks down work packages into greater detail. A subproject WBS generally is used when the project manager assigns a scope of work to another organization, and the project manager at that organization must plan and manage the scope of work in greater detail.