Slope = (Crash cost - Normal cost)/(Crash time - Normal time). This calculation shows the cost per day of crashing the project. The slope is negative to indicate that as the time required for a project or task decreases, the cost increases. If the costs and times are the same regardless of whether they are crashed or normal, the activity cannot be expedited.