Duration estimates may include contingency reserves, and contingency should be identified clearly in schedule documentation. They are built into the overall project schedule to account for uncertainty. They also may be developed using quantitative analysis methods. When more information is known about the project, the contingency reserve may be used, reduced, or eliminated.