Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
CBSE
CBSE Question Papers
NCERT Books
NCERT Exemplar Books
NCERT Study Notes
CBSE Study Concepts
CBSE Class 10 Solutions
CBSE Class 12 Solutions
NCERT Text Book Class 11 Solutions
NCERT Text Book Class 12 Solutions
ICSE Class 10 Papers
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Careers
Contact Us
Our Apps
Privacy
Test Index
PMP Certification Planning Questions Test 4
Show Para
Hide Para
Share question:
© examsnet.com
Question : 1
Total: 45
A project manager is working with a new quality manager to finalize the quality management plan. The quality manager suggests an expensive quality tool with which the project manager is unfamiliar. The project manager says there is a cheaper alternative, but the quality manager is adamant that there is not. To maintain the current schedule, the quality management plan and associated procurement must be completed the following week.
What should the project manager do next?
Evaluate the costs and benefits of employing the suggested tool
Request additional budget to fund the purchase of the quality tool
Escalate the problem to the sponsor for a final decision about the tool
Add the high cost of the quality tool as a risk to the register
Validate
Solution:
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Next Question