In this case, frequent changes are expected to be done by the team based on customer feedback. When a change is presented, a part of considering the change involves additional planning. The Project Manager and the team must examine how the change affects the project work and knowledge areas. Thus, Control scope ensures that the project scope is protected from unnecessary changes and all eligible changes are done using the scope change control system. Option A, Control Quality, is more focused on ensuring conformance to documented standards and is not the correct choice.