You typically find faulty work during quality control inspections and then you make recommendations to fix the problems. 1 is incorrect because you are not changing the project scope. 3 is incorrect because you are not requesting for the project scope to change with additional work. 4 is incorrect because you are not making actions to bring future results back into alignment with the project plan. You are fixing errors – this is defect repair.