You want to implement corrective actions to prevent the problem from happening again. 2 is incorrect because you are not following the change control system or preventing the problem from happening again. 3 is incorrect because you are Scotty’s supervisor when it comes to project discipline. 4 is incorrect. While this choice seems appropriate, not all of the project team members or the stakeholders are circumventing the change control system – just Scotty in this instance. As the project manager you need to address the problem directly. In addition, the question states that all of the project team members and the stakeholders are located throughout the US, not just in Phoenix.