The project manager is dealing with known unknowns. So he needs to create contingency reserves. The calculation will include calculating the Probability times impact of each of the risks separately and then adding them together. Delay in engineering : 0.40 x 300,000 = 120,0000 Delay in weather :0.50 x 150,000 = 75000 120,000 + 75000 = 195000