An imposed completion date will likely require you and the project team to schedule from the completion date. 1 is incorrect; there’s no evidence that you must work overtime to complete the project. 2 is incorrect; there’s no evidence that you will need to additional labor to complete the project by the schedule date. In addition, the work may not be affected by the added labor (considered activities of fixed-duration). 4 is incorrect. The scheduled completion doesn’t necessarily correlate to more funds to complete the project.